Lake Sammamish Waste Water Lift Station #3
This underground sewage lift station consisted of 3 200HP pumps. We provided all of the electrical for the building, the pumps, the controls, wet well and dry well telemetry systems. Most of the work was below the year round water table which required extra measures to keep water out of conduits and equipment.

Samm1.jpg   Samm2.jpg
Excavation for pump station   Conduits located between roof of pumping station and floor of access building

Samm1.jpg   Samm2.jpg
Lower level control room   Completed building with electrical service, blowers, and generator